Deadline of Submission of Bids (Bid Submission)

DLPC
DU Demand: 
55 MW Intermediate and RE power supply requirements for RPS compliance
DU Contract Period: 
Ten (10) years staring February 26, 2022, subject to the approval of the Energy Regulatory Commission
DU CSP Stage: 
Deadline of Submission of Bids (Bid Submission)

DLPC 2nd round of CSP for the procurement of 55 MW Intermediate (75% from eligible RE supply) for RPS compliance

Deadline of Submission of Bids (Bid Submission)

17 November 2021